Spring Park data centre upgrades
Client: Ark Data Centres
Ark Data Centres - Designing and operating data centres which empower businesses to work from anywhere in the world.
Location:
Corsham, Wiltshire
Duration
52 weeks
Contract value
£6.0M
Constructed
2022 to October 2023
The brief:
The Sweet Projects Corsham team have assisted ARK Data centre construction team on over 50 projects, ranging from fitting replacement upgraded lifts into existing Data centre buildings, Electric Vehicle charging points, asbestos removal and demolition, plus street lighting, and enhanced CPNI secure room wrapping. The range of projects have been carried out in the live environment of a highly secure Data centre. Logistically challenging but extremely rewarding when completed. Current projects include the construction of the new HV substation, switch room and backup Generator Farm, in readiness for future developments at Spring Park, namely P5 which has full planning and is due to commence construction in the second quarter of 2024. The Switch room and generator farm are on track for completion October 23.
Key challenges:
- Working alongside existing Data Centres users, without causing disruption & disturbance
- Enhanced security, for entry into site for work and delivery
The solution:
- Careful logistical planning, short term programming, sharing the challenge with a can-do attitude
- Daily briefings with a flexible approach to overcome issues that arise
- Appointed person to ensure all attending staff, trades and deliveries are booked in correctly for smooth operations