The Union Park data centre has over 2,700 piles in its foundation design across the whole date centre – the last of which was installed in February 2022.
The vast majority installed were Continuous Helical Displacement (CHD) method piles, which bring a reduction in waste going off-site and minimise the vibration output of the piling works. All part of our efforts to create sustainable data centres.
Ark would like to thank Sweet Projects and their piling specialist Roger Bullivant Limited for their hard work in completing this milestone on the project